Data Center - Scheduled Maintenance (GSC/Garden City, NY)

Scheduled Maintenance Report for Opti9 Technologies

Completed

The scheduled maintenance has been completed.
Posted Sep 13, 2026 - 16:00 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 13, 2026 - 08:00 EDT

Scheduled

Opti9 will be performing maintenance during the scheduled window to replace UPS fans.

No impact is expected but this is a significant maintenance with the potential for impact as we are touching core power distribution equipment.
Posted Sep 11, 2026 - 21:28 EDT
This scheduled maintenance affected: GSC - Cloud (Facilities - Power/Cooling - GSC).